Installation

The ZenRobotics Recycler is installed in a well defined and implemented project, lead by experienced professionals. ZenRobotics keeps the customer up to date during the whole project. That is why we pay extra attention to information flow, at all times.

Site operation kick-off

Site operation kick-off is started by organizing organization meetings and establishing active information exchange with the client. Site operation schedules for installation and testing is agreed on and safety instructions and procedures are checked on-site.

ZenRobotics Recycler Installation

Mechanical and electrical installation started when ZRR arrives at site. The work is usually done with a local partner, and takes about 5 – 10 days. The commissioning takes place after installation and the official acceptance protocol. During the whole process extra attention is paid to information sharing so that the customer always knows what is the status of the project.

ZenRobotics Recycler Test Trials

Preliminary ZRR Test trials are ran by ZenRobotics using manual waste infeed to make sure that every aspect of testing is covered. After these, the final testing is performed with the real customer process equipment and normal waste from the actual customer process.

ZenRobotics Helsinki Installation

The first ZenRobotics Recycler (pictured) installation has been in operation in Helsinki since February 2011, at SITA Finland, a part of SUEZ Environnement. If you would like to see the action yourself, why not book a site visit!